State of Alaska Project No. Z581060000 / Federal # 0211052
The following table shows the planned project schedule:
Environmental Assessment and Preliminary Engineering | 2014 - 2016 |
Final Design and Permitting | 2016 - 2024 |
Right-of-Way Acquisition | 2018 - 2022 |
Utility Agreements | 2020 - 2024 |
Phase 1 Construction, MP 157-161 | 2025 - 2027 |
Phase 2 Construction, MP 161-169 | 2027 - 2029 |